Functional Testing Demo Traceability

TABLE 2.4 · WORKED EXAMPLE

How is Req 2 coverage calculated?

Follow the traceability links, identify the passed test, and add the priority weights.

Test-to-requirement traceability

All six tests have been executed.

Test Priority Result Req 1 Req 2 Req 3
Test 12 Pass ×
Test 25 Pass ××
Test 31 Fail ××
Test 41 Pass ×
Test 54 Fail ×
Test 62 Fail ×

× means the test is associated with the requirement.

Priority is used as a weight: 1 = minor risk; 5 = critical risk. This example measures coverage using passed tests, as defined in the text.